| Estimates of the construction interval for a new Combined
Cycle (CC) unit range from 12 to 24 months. For example, my interviews of utility officials in 1998 indicated a one year lead time for construction. More recent information suggests the interval is longer. For example, several power company offcials intervied for the San Francisco Chronicle (1-30-01) estimated the construction interval at two years. A two year interval is also estimated in a recent EPRI Technical Report on the "Prospects for Boom/Bust in the US Electric Power Industry." |
Based on these expected completion dates, California would have 500+500+320 or 1,320 MW of additional capacity on line in the Summer of 2001. |