Expected to Apply: 5,920 MW

Power plants are entered on the CEC website as "expected" when the developer makes a public announcement about the plant.

A formal application for a construction permit is expected in the near future. The date when the developer might formally apply for a construction permit is included on the CEC website.

 
 Name Developer County

Size (MW)

 South City AES San Mateo

550

United
Golden Gate
El Paso
Merchant
San Mateo

570

Antelope Valley Enron Kern

1,000

Long Beach District  Enron  Los Angeles

 500

East Altamont Calpine Alameda

1,100

 Kern Power  North American  Kern

 160

Magnolia Repower  City of Burbank  Los Angeles

 310

 Roseville  Enron  Placer

 750

 Salton Sea Geothermal Cal ifornia
Energy Group
 Imperial

 300

Redondo Beach  AES  Los Angeles

 700