Naill's Model of Natural Gas Exploration
Naill's model was developed in Dynamo, the software described
in Appendix D in the book. A Stella version of his model is shown in Figure
4.

Figure 4. Stella version of Naill's 1973 model of the exploration and production
of natural gas.
In adapting the model to Stella, I have taken the liberty
of changing the units from cubic feet (CF) to trillion cubic feet (TCF).
I have also changed the variable names from the short names that are customary
with Dynamo to the longer names in Figure 4. Table 1 provides a comparison
of the names and units assigned to the stocks and flows in the two models.
Table 2 provides a similar comparison for the converters in the two models.
| Dynamo Names |
Old Units |
Longer Names for the Stella model |
New Units |
| UPR | CF | unproven reserves | TCF |
| PR | CF | proven reserves | TCF |
| AUR | CF/yr | average useage rate over past few years | TCF/yr |
| UR | CF/yr | usage rate | TCF/yr |
| DR | CF/yr | discovery rate | TCF/yr |
| Dynamo Names |
Old Units |
Longer Names for the Stella model |
New Units |
| AURAD | yrs | averaging interval for the useage rate | yrs |
| MAR | dim'less | cost margin | dim'less |
| COE | $/CF | cost of exploration | $/kcf |
| DRPR | yrs | desired reserves to production ratio | yrs |
| DD | yrs | discovery delay | yrs |
| EIIE | $/yr | effective investment in exploration | B$/yr |
| FURR | dim'less | fraction of unproven reserves remaining | dim'less |
| GC | 1/yr | growth constant | 1/yr |
| UPRI | CF | initial amount of unproven reserves | TCF |
| URI | CF/yr | initial useage rate | TCF/yr |
| IIE | $/yr | investment in exploration | B$/yr |
| COEN | $/CF | normal cost of exploration | $/kcf |
| PIEE | dim'less | percent invested in exploration | dim'less |
| URP | CF/yr | potential useage rate | TCF/yr |
| P | $/CF | price | $/kcf |
| RPR | yrs | reserve-production ratio | yrs |
| SR | $/yr | sales revenue | B$/yr |
| STC | $/CF | smoothed total cost | $/kcf |
| TC | $/cf | total cost | $/kcf |
| TCSD | yrs | total cost smoothing delay | yrs |
| cost of exploration multiplier | dim'less | ||
| DM | dim'less | demand multiplier | dim'less |
| percent invest. in exploration multiplier | dim'less | ||
| PM | dim'less | price multiplier | dim'less |
| ROIM | dim'less | return on investment multiplier | dim'less |